Update: Littlehampton Sea Defences, £400,000 Crane Bridge arrives

Littlehampton Sea Defences Crane Bridge 2The massive £400,000 Crane Bridge is currently being installed in Pier Road.

This enormous structure will carry the crane along Pier Road as it drives in each pile.

Littlehampton Sea Defences Crane Bridge 1Environment Agency’s sea defence contractor VolkerStevin appeared to have overcome, what has so far proved the greatest engineering challenge in the construction of  Littlehampton’s Sea Defences by creating this £400,000 crane bridge. You can read more about why the Crane Bridge has been needed here.

The Bridge has been especially created to carry the weight of the Crane along Pier Road while keeping weight off Pier Road by straddling the road and sitting on the piling structures.

Littlehampton Sea Defences Crane Bridge 8Here you can see the new crane bridge in position and being worked on to get it ready.

Once finished the crane will sit on this platform and will work it’s way along Pier Road.

Crane in Pier RoadOnce ready, this crane will be driven onto the Crane Bridge where it will begin the piling works in Pier Road. It’s a challenging job as once each ‘gateway of piles’ are driven in their final home in the river bed, the bridge will then have to be moved forward onto to these piles to begin on the next batch.

Piling gateThis is the ‘piling gate’ which the piles are loaded into before being driven into the ground.

Sea Defence construction Arun Parade 8Piles being driven into the ground, which have been loaded into the piling gate.

As you can see, it’s not an easy, or a quick task and when you see the sheer logistical problems you get an idea as why the project has been delayed so much.

Look and Sea!Littlehampton’s Look and Sea! Centre’s iconic viewpoint framed by the new Crane bridge.

Littlehampton Sea Defences Crane Bridge 6Work underway today (Wednesday, 19th February 2014) on installing the new crane bridge.

Littlehampton Sea Defences Crane Bridge 3The sheer size of this new crane bridge has to been seen in the ‘flesh’ to understand how vast it is. It will be an amazing sight to see the Crane on top of this bridge, and if Littlehampton ever needed a new visitor attraction, then this is it.

VolkerStevin have indicated that they expect Piling works to be completed in Pier Road by May 2014. Only once the piling has been completed can the works begin on the back filling and concreting necessary to create the actual ‘wall’ and capping that will sit both behind and above the piles.

It’s a long, challenging difficult engineering process.

Littlehampton Sea Defence Piling worksMeanwhile piling work continues at the harbour entrance. If you pop up there you can great views of what’s happening as you can in Pier Road.

Come and witness history being made.